Page 42 - U4SSC Compendium of practices on innovative financing for smart sustainable cities projects
P. 42

this transaction was carried out mainly through a syndicated financing structure, AFC may be
            legally restricted to share the terms and conditions negotiated with other lenders. However, the
            AFC contribution is fully through direct equity participation and shareholder loans, with favourable
            terms and conditions.



            Observations

            •  Leasing bandwidth to leading local telecom operators has generated activity and revenue for
                these companies, further promoting sector growth.

            •  In 2009, approximately 80 per cent of the voice and data traffic of Africa was carried by satellite,
                which was not suited for new broadband applications that required large bandwidth. The project
                solved this challenge by adopting a sophisticated technology to meet broadband capacity
                needs, increasing network capacity and efficiency. The Dense Wave Division Multiplex (DWDM)
                fiber optic system technology provided a design capacity of 1.28 Tbps, which is approximately
                10 times the speed capacity of other existing technologies.

            •  Early-stage equity contribution from AFC provided a de-risking opportunity resulting in a diverse
                group of international financiers and accelerated time-to-market. Unexpected incurred costs, or
                cost overruns, were mitigated by putting in place a standby funding contribution from investors.
            •  The project required development funding from major international institutions to reach
                bankability. Investors were hesitant to commit to a startup company that was planning to
                develop and implement a technologically advanced and complex project with multi-jurisdiction
                implications. Overcoming this challenge required a well-structured and well-developed project
                with a strong sponsor group, and credible international financial and technical partners.
            •  Differing regulatory regimes in countries of the project led to some delays in obtaining requisite
                operational licences and authorization. Approvals for licences, landing permits, environmental/
                waterways permits, and construction permits vary substantially per country. The cross-country
                nature of the project requires knowledge of differing regulatory and market requirements for
                its operation.
            •  At inception, the role that fibre-optic broadband systems can play in the social, economic and
                commercial activities and development in the countries was relatively less acknowledged and
                known. Consequently, the positive impact was generally underestimated by most countries but
                has significantly improved over time.

            •  The project has a potential impact on the marine and terrestrial environments. Overcoming this
                challenge required a detailed impact study that ensured operation with minimal impact to the
                environment and avoided any marine-protected areas. Close consultation with communities of
                the project, as well as provision of employment opportunities at the construction and operational
                phases ensured maximum buy-in of all the communities.

            •  At inception, attracting and retaining skilled personnel to a start-up enterprise was a major
                challenge for the project. Specialized training programmes were conducted to enhance capacity
                and ensure the successful operation of the project.



             30  Compendium of practices on innovative financing for SSC projects | January 2023
   37   38   39   40   41   42   43   44   45   46   47