2.2 Implementation
The application of the HITSystem was jointly conducted with the assistance of several partners including (but
not limited to):
Global Health Innovations (developers of this system)
Kenya Medical Research Institute
OnTarget (internet marketing company)
Academic Researchers (from University of Kansas Medical Center and Children’s Mercy Hospital
Kansas City)
Walter Reed US Military HIV Research Program (training and implementation)
NASCOP.
For the designated hospitals for the pilot project in Kenya, the HITSystem can be accessed on computers and
laptops, using mobile broadband, which eases the implementation of this system even in remote areas (if
required). The HITSystem has been built to generate regular alerts directed at health providers other EID
stakeholders and lab technicians, when time sensitive interventions are required in a particular child’s case.
These alerts are directed at tracking and identifying children who have omitted their treatments for a defined
period of time. An inbuilt text messaging mechanism in the HITSystem sends messages to mobile phones of
the parents when test results are ready or follow up visits for treatments are needed.
In Kenya, especially Nairobi, the HITSystem was implemented from April 2011 to November 2013 at certain
38
health facilities. The implementation and was conducted between April 2011 and May 2014.
The health facilities chosen for the pilot were selected based on the logistical feasibility, absence of other EID
39
related interventions for HIV and the approval from the respective hospital stakeholders.
2.3 Outcomes
This pilot project in Kenya has been carried out with remarkable ease and effectiveness. It was noted that
relatively limited penetration of ICTs, telecommunications and internet connectivity had a very minimal
negative impact on the continuance of the project. The sustained efforts stakeholders of the stakeholders
facilitated the successful adoption, implementation and continuous maintenance of the HITSystem. With the
monitoring mechanism in place, HITS was able to ensure that treatments were provided on time.
The principles of the HITSystem were found to be in line with EID guidelines and the results of this pilot
project surpassed the expectations and outcomes observed in national statistics. A feedback mechanism was
also incorporated into the implementation procedure of the HITS to ensure that the participants were
satisfied with the services received. This also helped improve the existing line of treatments and reduced
response time for emergencies.
It was noted that the HITSystem successfully reached nearly all mother–infant pairs, who were enrolled in
EID services at the targeted health facilities. However, it was observed that nearly 40% of HIV-exposed infants
40
in Kenya are never enrolled in EID, thereby not receiving the benefits of HITS.
____________________
38 The follow-up periods for this process ranged between 6 and 38 months depending on month of initial
implementation of the designated facility.
39 Lessons learned from implementing the HIV infant tracking system (HITSystem): A web-based intervention to
improve early infant diagnosis in Kenya. 2015.
40 Lessons learned from implementing the HIV infant tracking system (HITSystem): A web-based intervention to
improve early infant diagnosis in Kenya. 2015.
132 U4SSC series