GENERAL SCHEDULE OF THE WORK OF THE CONFERENCE
Subject to change according to the progress made

Week 1 (27 - 31 October)
Organization and commencement of work in Committees and Working Groups

Week 2 (3 - 7 November)
Continuation of work in Committees and Working Groups

Friday 7 End of work of Plenary Working Group 2
  End of work of Working Groups 5A and 5C

Week 3 (10 - 14 November)
Continuation of work in Committees and Working Groups as well as Plenary meetings to consider output of Committees 4 and 5

Monday 10 End of work of Working Group 4B
Wednesday 12 End of work of Working Group 5B
Friday 14 End of work of Working Groups 4A and 4C
  End of work of Plenary Working Group 1

Week 4 (17 - 21 November)

Monday 17 End of work of Working Group 4D
  End of work of Committee 3
Tuesday 18 End of work of Committee 4
  End of work of Committee 5
  Report of Committee 2
  Report of Committee 3
Wednesday 19 First reading by Plenary of last texts of the Final Acts
Thursday 20 Second reading by Plenary of last texts of the Final Acts
Friday 21 Signing ceremony and Closing
Note 1 – Plenary meetings will be scheduled as necessary during each week of the Conference
Note 2 – This schedule may be changed in the course of the work of the Conference